04 January 2019 - The five pillars on the Moračica bridge, which is also the most demanding structure of the first section of the highway from Smokovac to Mateševo, will be connected by the beginning of summer 2019. More than 130 workers constructed the bridge, and there are many difficulties within the construction process, such as the height and the weather conditions.
Despite the strong wind that is characteristic of Bioče area, 130 workers do construction works on one of the highest bridges within the region, each day at the height of 160 meters.
About 30,000 cubic meters of concrete will be used for the Moračica's span construction, while 5,000 tons of reinforcement will be installed within the construction.
"The spanning structure is built from all pillars, and it is connected in the middle. About one segment of three and a half meters is built for about ten days, which means that we are looking forward to the beginning of the summer when the span construction will be complete, “chief Section 1 engineer Duško Rondović said to the National News Agency TVCG.
After that, asphalting and construction of the reflecting fence and installations on the bridge will begin. During the asphalting process, travelers will be able to get from Moračica to Podgorica through the Mrka tunnel and the Mrka bridge.
"The left bridge is practically complete; the span construction is connected. It remains to build four segments on the right side of the bridge. We expect this to be complete sometime in the spring. In front of this bridge there is the Mrka tunnel where we have just finished the secondary coating, "said Rondović.
In addition to the tunnel Mrka, in the so-called first section of the highway, there will be two more tunnels - Suka and Verešnik, and a total of 300 workers are engaged in the construction works.